Summary
Delivery watch: 4 milestone(s) and 10 task(s) past due. Created 0 recovery task(s).
Evidence — records this run consulted (14)
- ▸Milestone past due: Content migration complete (Harbourview website rebuild) — was due 2026-07-11(project #1)
- ▸Milestone past due: Launch (Harbourview website rebuild) — was due 2026-07-24(project #1)
- ▸Milestone past due: Brand guidelines delivered (Meridian brand + site) — was due 2026-07-26(project #2)
- ▸Milestone past due: Site wireframes approved (Meridian brand + site) — was due 2026-08-03(project #2)
- ▸Task overdue: Migrate blog articles to new CMS — was due 2026-07-10(task #1)
- ▸Task overdue: QA checkout + booking flows — was due 2026-07-19(task #2)
- ▸Task overdue: Set up launch redirects — was due 2026-07-22(task #3)
- ▸Task overdue: Collate brand questionnaire responses — was due 2026-07-13(task #4)
- ▸Task overdue: Prepare typography options — was due 2026-07-20(task #5)
- ▸Task overdue: Send Solstice revised proposal — was due 2026-07-15(task #6)
- ▸Task overdue: Recovery plan: Content migration complete — was due 2026-07-15(task #7)
- ▸Task overdue: Recovery plan: Launch — was due 2026-07-26(task #8)
- ▸Task overdue: Recovery plan: Brand guidelines delivered — was due 2026-07-28(task #9)
- ▸Task overdue: Recovery plan: Site wireframes approved — was due 2026-08-05(task #10)